From the administrators' statement
The Company was incorporated in 2013 to carry out the redevelopment of a Grade A listed schoolhouse in Broughty Ferry into residential accommodation.
The company engaged a main contractor to commence work on the development in April 2015. The main contractor entered Administration 10 days before work was to commence and an alternative main contractor was engaged to commence work in May 2015. The development was initially scheduled to complete in February 2016 however issues arose from the main contract and practical completion was not achieved until November 2016.
The main contract issues delayed the completion of the site and affected the availability of funding while matters were unresolved.
Administrators' statement of proposals (2017-04-07) · Companies House register