Buttimer Engineering UK Ltd (10594870): administration
- Status
- Administration ended
- Administration began
- 2020-01-17
- Incorporated
- 2017-02-01
- Location
- Manchester
- Industry
- 43290 Other construction installation
Why it went into administration
- Supply chain disruption
- Creditor pressure / legal action
- Bad debts / customer insolvency
From the administrators' statement
The Company was incorporated on 1 February 2017 to consolidate and transact a growing portfolio of work in the UK.
The Company's operations included the supply of specialist equipment, replacement of grain handling equipment, installation of dust extraction and fuel forwarding systems and engineering services in relation biomass silos. It successfully completed a number of substantial UK contracts.
In May 2018, the Company entered into a €8.6m fixed price labour only contract (“the Contract”) to erect the fuel handling systems at Tees Renewable Energy Piant (“the Teeside Project’). The direct contractor retained the procurement and design elements of the contract. During the initial stages of the contract the direct contractor encountered significant delays and difficulties with their supply chain.
Administrators' statement of proposals (2020-03-23) · Companies House register